Drone footage at Mille Lacs Band of Ojibwe D1 Health Clinic.  The construction site has been staked and all storm water and sediment controls are in place.  The job trailer has been placed as well as all underground utilities.  Exterior footings and foundation walls are almost complete.  The entry canopy and elevator footings and foundations are all that’s left to be poured before moving on to erecting steel.  Construction is progressing quickly!